Delta M&E supplied refrigeration equipment and associated systems through an engineering partner for a PRAN beverage manufacturing project in Bangladesh. The recorded scope included a YORK RWK II 40-CMTAY135CK unit, auxiliary equipment and propylene glycol circulation systems.
Equipment and auxiliary systems supplier through an engineering partner
Record type
Historical order record
The recorded supply scope includes equipment, circulation systems, electrical controls, piping materials, insulation, transportation and engineering installation guidance. YORK identifies the main refrigeration unit; the other listed equipment and systems are not presented as YORK products.
Complete recorded supply scope
Refrigeration equipment
YORK RWK II 40-CMTAY135CK refrigeration unit
SWL-700 evaporative condenser
ZA-2.0 high-pressure liquid receiver
Semi-welded plate heat exchanger
AF-150 gas-liquid separator
FZA-2.4 thermosiphon receiver
XA-133 emergency ammonia release device
JY150 oil collector
Propylene glycol circulation systems
Propylene glycol low-carbon steel tank and insulation
Propylene glycol circulation pumps
Propylene glycol supply pumps
Internal tank circulation piping system and valves
Electrical and control systems
Star-delta low-voltage starter cabinet
Auxiliary equipment power distribution and control panel
Propylene glycol pump startup and temperature monitoring
Equipment power and control wiring
Piping, valves and insulation
Shut-off valves, solenoid valves and filters
Refrigeration piping system
Equipment, vessel and piping insulation
External cladding for equipment and piping insulation
Equipment and piping supports
Associated services
Equipment transportation
Engineering installation guidance
Explore HVAC equipment
Current product series are procurement references and are not substitutes for the exact equipment supplied to this project.